WORK ORDER WORKSHOP REPORT - 28/Jun/2024 02:20 PM haive@evolutionerp.com.au
W/O Number:WS18062024-4Job Number:33585
Date Issued:28/Jun/2024 02:20 PMDate Required:15/Jun/2024 12:00 AM
W/O Raised By:HaiveClient:SHAFA - SHANE FARRELL
Job Location:NATIVE BRUSH FENCING Tubigon VIC NATIVE BRUSH FENCING Tubigon VIC


NOMINAL WIDTH3000
NOMINAL HEIGHT1000
CHAIN LINK50x3.15 Heavy Galvanized
SELECTED CHAIN LINK FABRIC HEIGHT[12 LESS 0.5 DIAMOND] 1014
ACTUAL FRAME HEIGHT
*GATE FRAME GALVANIZED FINISH

Cut Crown Bar DN32-XLG :: 1 X 4779 mm
Bend Crown Bar
BOTTOM RAILS [VOGEL CUT]DN32-XLG: 1 X 2898 MM
CENTRE RAILS
VERTICAL BRACES[VOGEL CUT]DN25-XLG: 2 X 931 MM
DRILL HOLE FOR SHOOT BOLT828 MM

ITEM PIPE WORKSHOP CUTTING & BENDING (STAGE 1) NUMBER OF UNITS MINUTES PER UNIT TOTAL MINUTES
DN32-XLG CUT CROWN BAR RAILS 1 1.5 1.5
DN32-XLG BEND CROWN BAR 2 5 10
DN32-XLG CUT BOTTOM RAILS 1 1.5 1.5
CUT CENTRE RAILS 0 0 0
DN32-XLG CUT VERTICAL BRACING 2 1.25 2.5
VOGEL NOTCH BOTH ENDS OF BRACING RAILS 3 1 3
DRILLING SHOOT BOLT HOLE 1 2 2
TOTAL CUT & PREP TIME FOR GATE FRAME 20.5

ITEM PIPE WORKSHOP WELDING GATE FRAMES (STAGE 2.A) NUMBER OF UNITS MINUTES PER UNIT TOTAL MINUTES
SETUP TIME ON WELDING BENCH (TACKING FRAME) 6 1 6
DN32-XLG WELD OUTER FRAME 2 5.5 11
WELD INTERNAL RAIL 0 0 0
DN32-XLG WELD VERTICAL BRACING 4 4.5 18
TOTAL WELDING TIME FOR GATE FRAME ONLY 35
ITEM CODE IMAGE WORKSHOP GATE FITTINGS (STAGE 2.B) NUMBER OF UNITS MINUTES PER UNIT TOTAL MINUTES
H8032D TWO PART INTERLOCKING HINGES + ATTACHMENT - GALVANISED 2 1 2
GEB12-SL "SINGLE (""L"" SHAPE) HAND HOLE (FOR TOP OF MID RAIL) ( 12MM ROD - 90MM X 186MM) FOR STANDARD SINGLE GATE SHOOT BOLT- GALVANISED" 1 1 1
GDB370 SHORT DROP BOLTS - GALVANISED 1 1 1
B8 SHOOT BOLT (WITH SLIDE PLATE) - GALVANISED 1 2 2
HCR HINGE COLLAR 1 3 3
TOTAL WELDING TIME FOR SELECTED WELD ON GATE FITTINGS ONLY 9
ITEM WIRE UP GATE FRAMES (STAGE 3) NUMBER OF UNITS MINUTES PER UNIT TOTAL MINUTES
STEP 1 DE-SCALE WELDS & PRIME PAINT ALL WELDS 6 1 6
STEP 2 FIT CHAIN LINK TO GATE FRAME BASED ON M2 3SQM 2 6
STEP 3 TRIM & KNUCKLE CHAIN LINK TO BOTTOM RAIL M 2.9 2.5 7.25
STEP 4 SHAPE IN HAND HOLES 1 1 1
STEP 5 LOAD UP GALV LACING WIRE TO NEEDLE KG 0.47 KG 4 1.88
STEP 6 LACE UP PERIMETER OF GATE FRAMES 8M 5 40
TOTAL LACING TIME FOR GATE FRAME ONLY 62.13 MIN
SETUP TIME ALLOWANCE BETWEEN STAGES 1 TO 3 18
TOTAL O/ALL MINUTES ALLOWED FOR MANUFACTURER OF GATE (BASED ON CURRENT STANDARDS) 144.63