Workorder Number:WS02072024-2 Job Number:33589 Date:4/Jul/2024 01:12 AM |
| Gate Number | Opening Size | O/all Gate Frame Height | Pipe | Chainlink | Opening Side | Cost |
|---|---|---|---|---|---|---|
| 1 | 5400 | 1912 | DN40-XLG | Heavy Galvanized 50x3.15 KK | LH | 755.36 |
| Material | Code | Qty | Cost | Total |
DN40-XLG
|
PXLG40-6500 | 14.22 | $78.98 | $172.97 |
DN25-XLG
|
PXLG25-6500 | 12.38 | $47.39 | $90.04 |
FBG5005
|
FBG50056 | 5.66 | $55 | $311.30 |
50x3.15
|
CLHG210050315KK | 9.72 | $12.4 | $120.53 |
Heavy Galvanized
|
LWHG2001KG | 0.94 | $2.3278 | $2.19 |
GDB370
|
GDB370 | 1 | $4.5465 | $4.55 |
HCR
|
HCR | 1 | $0.5 | $0.50 |
| Standard Fittings | ||||
| Custom Fittings | ||||
| TOTAL CUSTOM FITTING COST | $0 | |||
| TOTAL FITTING COST | $0 | |||
| TOTAL MATERIAL COST | $702.07 | |||
| Item | Time(min) | Rate/hr | Total |
| Stage 1, Cutting, Notching | 40.25 | 90 | 60.38 |
| Stage 2.A & 2.B Welding | 141.5 | 90 | 212.25 |
| Stage 3. Lacing Chain Link to Gates | 123.2 | 90 | 184.8 |
| Set Up Time Between 3 Stages @ 6.0 min | 18 | 90 | 27 |
| TOTAL WORKSHOP LABOUR COST | 484.43 | ||
| Summary of waste factor cost | ||
| Item | Rate (%) | Cost |
| Chain-link | 0% | 0 |
| Lacing wire | 0% | 0 |
| Pipe | 0% | 0 |
| Tube | 0% | 0 |
| Total waste factor | 0 | |