logo
Cost Report

To,
VINES - Vines I.T.
TBA
TBA, TBA, TBA
TBA,

Workorder Number:WS02072024-2

Job Number:33589

Date:4/Jul/2024 01:12 AM


Summary List of Gate Size

Gate NumberOpening SizeO/all Gate Frame HeightPipeChainlinkOpening SideCost
154001912DN40-XLG Heavy Galvanized 50x3.15 KK LH 755.36


Summary of Material Cost
Material Code Qty Cost Total
DN40-XLG
  • DN40 Galv Pipe - XLG
  • 40 NB (48.3 O/D X 2.30MM) EXTRA LIGHT GALV PIPE 6500MM LENGTH
  • OUTER PIPE
PXLG40-6500 14.22 $78.98 $172.97
DN25-XLG
  • DN25 Galv Pipe - XLG
  • 25 NB (33.7 O/D X 2.00MM) EXTRA LIGHT GALV PIPE 6500MM LENGTH
  • HORIZONTAL PIPE
  • VERTICAL PIPE
PXLG25-6500 12.38 $47.39 $90.04
FBG5005
  • DIAGONAL FLAT BRACE
  • FLAT BAR 50 x 5MM @ 6000MM LONG GAL
FBG50056 5.66 $55 $311.30
50x3.15
  • Chainlink
  • 2091 H x 50 x 3.15MM (KK) - HEAVY GALVANIZED CHAIN-LINK FABRIC
CLHG210050315KK 9.72 $12.4 $120.53
Heavy Galvanized
  • Lacing Wire
  • LACING WIRE, HEAVY GALVANIZED, 2.00MM WIRE DIA. PER KG .
LWHG2001KG 0.94 $2.3278 $2.19
GDB370
  • SHORT DROP BOLTS - Galvanised
  • DROP BOLT, 370MM X 16 DIA, GAL
GDB370 1 $4.5465 $4.55
HCR
  • Hinge Collar
  • HINGE COLLAR, 20MM
HCR 1 $0.5 $0.50
Standard Fittings
Custom Fittings
TOTAL CUSTOM FITTING COST $0
TOTAL FITTING COST $0
TOTAL MATERIAL COST $702.07



Summary of Labour Cost.
Item Time(min) Rate/hr Total
Stage 1, Cutting, Notching 40.25 90 60.38
Stage 2.A & 2.B Welding 141.5 90 212.25
Stage 3. Lacing Chain Link to Gates 123.2 90 184.8
Set Up Time Between 3 Stages @ 6.0 min 18 90 27
TOTAL WORKSHOP LABOUR COST484.43



Summary of waste factor cost
Item Rate (%) Cost
Chain-link 0% 0
Lacing wire 0% 0
Pipe 0% 0
Tube 0% 0
Total waste factor0

Total Cost: 755.36