Office Use Only NCR Number # |
Copy of NCR in job pack(tick): |
| CUSTOMER DETAILS: |
ACT Building and Maintenance Pty Ltd |
|
|
| Work Order # 5992 |
Job # 7006 |
| DATE IN |
Wed 10 Apr 2024 |
| DATE REQUIRED |
Mon 06 May 2024 |
|
ITEM TO BE MANUFACTURED |
| CODE |
DESCRIPTION |
QTY |
COMPLETE |
| 1. DIP2124ACT |
Diplomat ACT spec Duck Bill - 2100H x 2400W - 140c - steel Color: Black |
124 |
|
| RECORD MATERIAL USED (BOM) |
| CODE |
DESCRIPTION |
ALLOC. |
ACTUAL |
| ACT-PIC |
ACT Duck bill picket 25x25x1.2x2100 long raw |
17.0000 |
|
| DPRAIL-40-1.6-24-140-IMP |
Double Punched Rail 40 x 40 x 1.6 x 2400mm - 140 C - Imported |
2.0000 |
|
| PC-STANDARD |
POWDER COATING OF CHAINLINK GATES FRAMES, TUBULAR AND WELDMESH PANELS. RATE PER METER SQUA |
5.0400 |
|
| IMP-CLIP |
IMPORT PLASTIC PACKING CLIP FOR DIPLOMAT PANELS |
6.0000 |
|
| |
|
|
|
| |
|
|
|
| |
|
|
|
| RECORD TIME |
| WORK PROCESS |
ALLOWED |
QTY |
DAY1 |
DAY2 |
DAY3 |
DAY4 |
| Picket Machine |
10.00 (MIN.) |
0 |
|
|
|
|
| WELDING- PANELS |
15.00 (MIN.) |
0 |
|
|
|
|
| Powdercoating |
10.00 (MIN.) |
0 |
|
|
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
NOTES:Notes |
| ALL DIMENSIONS ON DRAWINGS TO BE RECORDED & INITIALLED DURING FAB and MACHINING |
| WORK INSTRUCTIONS |
Target Time frame |
MUST BE COMPLETED BY WORKER |
FMS Checked by |
Equipment Calibrated by |
Start size (Dia.) |
FMS (Dia.) |
Length metal sprayed |
Time taken |
Worker initials |
|
|
Calibrate & Write down your start & finished machine sizes for ALL diameters! |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
| | | | | | | | |
Hold points to be utilised = prep size to be included in job instructions and checked before spraying, size after spraying to be checked, and job to be checked before taking off borer after finish cut. |
| | | | | | |
| | | | | | |
| Have returned all tooling to the correct location? Y / N |
|
| JOB PACKING CHECKLIST |
Name of person packing ______________________ |
Date packed _________________________ |
|
Pallet – (circle) New or Used |
Weight of job _________kg Weight marked on job |
Is job secured with PTE strapping? |
Is rubber between strapping & job? |
Is job wrapped in plastic? |
|
| QUALITY CONTROL - FINAL INSPECTION UPON JOB COMPLETION |
| Supervisor: |
Date Inspected: |
|