Cost Report

To,
NSW010 - NSW Department of Education
TBA
TBA, TBA, TBA
TBA,

Workorder Number:WS18112024-1

Job Number:22745

Date:11/Mar/2025 01:21 PM


Summary List of Gate Size

Gate NumberOpening SizeO/all Gate Frame HeightPipeChainlinkOpening SideCost
130001900DN32-XLG Heavy Galvanized 50x3.15 KK LH 451.97


Summary of Material Cost
Material Code Qty Cost Total
Outer Pipe Cost DN32-XLG 9.44 5.29 49.94
Horizontal Pipe Cost DN25-XLG 2.89 4.14 11.96
Vertical Pipe Cost DN25-XLG 3.57 4.14 14.78
Chain-Link Cost 50x3.15 5.4 6.09 32.89
Lacing Wire Cost Heavy Galvanized 0.58 3.28 1.9
Total111.47
Standard Fittings
TWO PART INTERLOCKING HINGES + ATTACHMENT - Galvanised H8032D 2 10.1535 20.31
"Single (""L"" Shape) HAND HOLE (for top of mid rail) ( 12mm Rod - 90mm x 186mm) for standard Single Gate Shoot Bolt- Galvanised" GEB12-SL 1 2.2785 2.28
SHORT DROP BOLTS - Galvanised GDB370 1 5.6385 5.64
SHOOT BOLT (with Slide Plate) - Galvanised B8 1 3.71 3.71
Hinge Collar HCR 1 0.5 0.5
Total Standard Fitting Cost32.44
Custom Fittings
Total Custom Fitting Cost 0
Total Fitting Cost 32.44
Total Material Cost 143.91



Summary of Labour Cost.
Item Time(min) Rate/hr Total
Stage 1, Cutting, Notching 28.75 90 43.12
Stage 2.A & 2.B Welding 83.5 90 125.25
Stage 3. Lacing Chain Link to Gates 75.12 90 112.68
Set Up Time Between 3 Stages @ 6.0 min 18 90 27
TOTAL WORKSHOP LABOUR COST308.05



Summary of waste factor cost
Item Rate (%) Cost
Chain-link 0% 0
Lacing wire 0% 0
Pipe 0% 0
Tube 0% 0
Total waste factor0

Total Cost: 451.97