Cost Report

To,
VIN001 - VINES IT
TBA
TBA, TBA, TBA
TBA,

Workorder Number:WS03072024-1

Job Number:22704

Date:5/Jul/2024 12:47 AM


Summary List of Gate Size

Gate NumberOpening SizeO/all Gate Frame HeightPipeChainlinkOpening SideCost
160001912DN40-XLG Heavy Galvanized 50x3.15 KK LH 791.04


Summary of Material Cost
Material Code Qty Cost Total
Outer Pipe Cost DN40-XLG 15.42 6.9 106.4
Horizontal Pipe Cost DN25-XLG 5.87 4.14 24.3
Vertical Pipe Cost DN25-XLG 7.11 4.14 29.44
Chain-Link Cost 50x3.15 10.8 6.09 65.77
Lacing Wire Cost Heavy Galvanized 1.02 3.28 3.35
Total229.26
Standard Fittings
Diagonal Flat Brace FBG5005 6.23 9.389 58.49
SHORT DROP BOLTS - Galvanised GDB370 1 5.6385 5.64
Hinge Collar HCR 1 0.5 0.5
Total Standard Fitting Cost64.63
Custom Fittings
Total Custom Fitting Cost 0
Total Fitting Cost 6.14
Total Material Cost 293.89



Summary of Labour Cost.
Item Time(min) Rate/hr Total
Stage 1, Cutting, Notching 40.25 90 60.38
Stage 2.A & 2.B Welding 141.5 90 212.25
Stage 3. Lacing Chain Link to Gates 131.68 90 197.52
Set Up Time Between 3 Stages @ 6.0 min 18 90 27
TOTAL WORKSHOP LABOUR COST497.14



Summary of waste factor cost
Item Rate (%) Cost
Chain-link 0% 0
Lacing wire 0% 0
Pipe 0% 0
Tube 0% 0
Total waste factor0

Total Cost: 791.04